Move-in weekend ends the roofing season on a campus. Trucks fill the lanes, families fill the lots and cranes have nowhere to stand. A reroof in Bellingham, WA that runs one week past the date is not a week late. It is a month late, because the next quiet window is winter break and winter is wet.

We build the campus bid backward from that weekend. Send us the drawings, the academic calendar and the facilities office's target dry-in window. We will price every termination, access item and phase before the bid closes.

Overview

College and University Roofing

Three campuses, three calendars

Bellingham has a large institutional building base. Western Washington University has more than 16,000 students and about 2,060 employees. Whatcom Community College and Bellingham Technical College add more. Each school runs its own terms, breaks and summer programs.

That means three calendars. A university may hold summer conferences that fill dorms and halls. A community college may run summer sessions in some buildings. A technical college runs labs and shops through the year. A roof plan must read each calendar before it picks a window.

Western's campus sits beside downtown and Sehome. Work near Sehome and Western Washington University brings street access and staging questions. Whatcom Community College sits in the north-side district near Cordata, where access is a different problem.

Summer conferences can fill halls that the roof plan assumed would be empty. We confirm room use building by building, and we re-confirm in May.

Old halls, new labs

A campus holds many building eras. Older halls may have built-up roofs with multiple layers. Newer science and student buildings may carry single-ply membranes, rooftop labs and vented hoods. Each has a different failure pattern.

We catalog them. The first walk records the system, the age, the penetrations and any moisture. We note exhaust hoods, because chemical exposure changes sheet choice. We note skylights and atriums, because glazing leaks are common and hard to trace. We note green-roof or solar plans, because they add load and penetrations.

The campus roof map that results lets facilities rank buildings by risk. It also guides a long-range plan. A roof asset management file turns scattered leaks into a funded schedule.

Labs deserve their own paragraph. A roof over a wet lab carries exhaust stacks, make-up air units and sometimes chemical storage vents. Fumes can attack some membranes. We ask facilities for the exhaust list before we pick a sheet. An office building style roof with a few units is simple. A lab roof with forty penetrations is a different bid.

Offices and classrooms are quieter. Their roofs are usually plainer, and they can take a recover more often. The map separates the two so the budget does not average them.

Skylights and atriums deserve a close look. Glazing joints move with temperature, and sealant ages fast on a south-facing slope. We test them with water before and after the work, and we log the result beside the curb it belongs to.

What moves the price

Six items move a campus roof price. They are deck condition, insulation, penetrations, access, phasing and safety. Insulation depth on a new campus roof follows the energy code in force from March 15, 2024, and every added inch lifts the flashing at curbs and walls. Thicker board lifts flashing heights. Penetrations are many on lab roofs. Access is the campus problem. Walkways, bike routes and service drives limit crane picks. Hauling material across a quad costs labor hours. Phasing follows classes and labs. A lab that cannot lose its fume hood for a day changes the plan.

A commercial roof inspection on every building ahead of the bid pays off. It converts guesses into allowances, and the facilities office can fund the right buildings first.

Contingency needs a plain line. Deck condition is unknown until the old roof comes off. We carry an allowance and a unit rate for deck repair. The campus sees the number before award and knows how a surprise is priced. State and public rules may require change orders to follow a set path, and we follow it.

The dry window is the break

About 34.8 inches of rain fall on Bellingham in a year. November is wettest and July driest, and the academic break lines up with the dry months. With only about 1,866 sun hours a year, a deck stays damp longer than a schedule hopes. Summer break lines up with the dry months. That alignment is why campuses build in summer.

It also makes the window crowded. Every building on a campus wants the same weeks. Crews are limited. We phase the work by priority and book the crew early. The worst roof goes first. Lower-risk roofs fill the rest of the window or move to the next year.

If a roof cannot wait, we plan a wet-season approach. Small areas open and close the same day. Material stays under cover. The bid shows the added cost so the campus can choose.

Winter break is a second, weaker window. Days are short, rain is frequent and decks stay damp. We use it for interior-facing work, small repairs and prep. Major reroofs wait for summer.

Wind on tall buildings

A 67 mph gust in March 2016 shows the wind a tall campus building can see. The November 2024 bomb cyclone sent easterly wind through Sudden Valley and tested loose screens and caps. Tall buildings meet wind early. Edge fastening is its own bid line on a campus roof. Metal gauge and fastener spacing are written into the scope. Seams get a probe and caps get a pull test. Historic or visible roofs, such as those with standing seam metal, get matching profiles and color on request. Design review adds weeks, and we flag it at the first walk.

Rooftop screens and louvers get their own check. A loose panel in a gale can strike a pedestrian walk. We tighten and log them at each visit. Antennas and solar frames added by research groups are checked for fasteners too.

Punch walk and campus records

The punch walk happens before classes start. At the punch walk we probe seams, test caps and flood the drains. Open items carry a name and a date until facilities signs them off. Facilities signs off.

The campus receives a roof map, photos and a penetration log. Researchers add equipment over time. Each new hole gets flashed and logged. Public institutions often hold records for audits, and the file serves that need. A school district uses a similar file for its buildings. The same method serves public agencies with many roofs.

A spring check each year keeps the log current. Seams are re-probed, drains cleared and photos retaken, so a leak report in fall matches against a clean baseline.

Commercial Roofing Questions

How do you schedule around move-in weekend?

We work backward from the weekend. Punch walk, final metal and cleanup finish before trucks arrive. The bid shows the float.

Can labs stay open during a reroof?

In most cases. We coordinate with lab managers, protect intakes and phase the work around hoods and equipment that cannot stop.

What if a building has multiple roof layers?

We take core samples to find the layer count and moisture. The code limits layers, and the answer decides recover versus tear-off.

How do you handle design review on visible roofs?

We identify review needs at the first walk, prepare profile and color submittals and carry the review time on the schedule.

What does facilities receive at closeout?

Facilities receives the roof map, photo set, penetration log and the signed punch list. The file feeds the long-range roof plan.

What happens when a researcher adds equipment after the reroof?

The facilities office calls us before the cut. We flash the new penetration, log it and confirm the warranty terms stay in force.

Send the drawings and the academic calendar

Send the roof plan, the spec and your target dry-in window. We will price every termination, access item and phase before the bid closes.